The State of Connecticut Department of Transportation (CT-DOT) is planning to mill and pave Cedar Rd./Rte. 53 from Chestnut Hill Rd. to the Weston town line. The State is also planning to pave into Weston on Norfield Rd. up to Weston Rd. (State Rte. 57).

Milling work will begin on or about Wednesday, June 5. This portion of work will take approximately one week (weather permitting). Paving work will begin on or about Monday, June 10, and will also take approximately one week (weather permitting).

The hours of operation will be from approximately 7 a.m. to approximately 5 p.m. each work day.

A CT-DOT inspector will be onsite during this time. Anyone with immediate questions about the work ahead of time or while work is in progress can reach out to the State inspector onsite or call the DOT office at 203.227.7692.