The CT Department of Transportation has set a tentative schedule for re-surfacing the stretch of Route 7/Danbury Rd. between Wilton High School and Route 107/Redding Rd..

The majority of the work will occur during overnight hours; specific start and end times are not yet available, however.

Road milling is tentatively scheduled to begin the night of Monday, June 18 and end the morning of Friday, June 22. Road paving is tentatively scheduled to begin the night of Sunday, July 8 and end the morning of Tuesday, July 17.

Wilton Police say the scheduled dates are tentative and adjustments will be made for inclement weather.